CSC, 13.9.2006 1 Status of HIPPI – September 2006 Maurizio Vretenar Alessandra Lombardi.

16
1 CSC, 13.9.2006 Status of HIPPI – September Status of HIPPI – September 2006 2006 Maurizio Vretenar Alessandra Lombardi

Transcript of CSC, 13.9.2006 1 Status of HIPPI – September 2006 Maurizio Vretenar Alessandra Lombardi.

Page 1: CSC, 13.9.2006 1 Status of HIPPI – September 2006 Maurizio Vretenar Alessandra Lombardi.

1 CSC, 13.9.2006

Status of HIPPI – September 2006Status of HIPPI – September 2006

Maurizio Vretenar Alessandra Lombardi

Page 2: CSC, 13.9.2006 1 Status of HIPPI – September 2006 Maurizio Vretenar Alessandra Lombardi.

2 CSC, 13.9.2006

HIPPI in 2006HIPPI in 2006

- Exactly mid-way through the project

- 8 deliverables and 4 milestones in 2006: large # of deliverables

0

2

4

6

8

10

12

14

16

18

2004 2005 2006 2007 2008

Deliverables

Milestones

Milestones Deliverables Total2004 1 0 12005 16 1 172006 4 8 122007 5 9 142008 1 13 14

58

Page 3: CSC, 13.9.2006 1 Status of HIPPI – September 2006 Maurizio Vretenar Alessandra Lombardi.

3 CSC, 13.9.2006

2006 Milestones and Deliverables2006 Milestones and Deliverables

WP2 CCDTL Prototype design, constr., test Jun-06: Prototype ready H-DTL Prototype design, constr., tests Dec-06: Prototype ready CCDTL Prototype design, constr., test Dec-06: Design report

WP3 Cavity B ready Jun-06: Cavity B ready

WP4 Chopper B Prototype design and constr. Jun-06: Design report Chopper A Prototype ready Aug-06: Prototype ready

WP5 Code preparation for 3 MeV test stand Jun-06: Intermediate report Profile measurement by fluorescence Jul-06: Final report Simulations and experiment at UNILAC Dec-06: Final report Non-interceptive bunch measurement Dec-06: Final report Collimators design Dec-06: Prototype ready Collimators design Dec-06: Final report

DELAYED 2005 MILESTONES 2.4.1 Construction of CCDTL pre-prototype, Jun 2005 Dec 2005 in prep.

intermediate report

3.3.1 Report on CH tuners Jun 2005 Sept 2005 Jun 2006

4.1.1 Chopper A Design Report Jun 2005 Dec 2005 with 4.1.2

4.1.2 Chopper intermediate test report Mar 2005 Mar 2006 Jun 2006

4.2.2 Dump design report Jun 2005 Oct 2005 in prep.

Dec. 06

Dec. 06

OK

Feb. 07Dec. 06

Oct. 06

?Oct. 06

OKOK

Page 4: CSC, 13.9.2006 1 Status of HIPPI – September 2006 Maurizio Vretenar Alessandra Lombardi.

4 CSC, 13.9.2006

Status of Milestones - DeliverablesStatus of Milestones - Deliverables

List prepared by AL with links:WP2: NORMAL CONDUCTING STRUCTURES

Milestones Deliverables

Comments Contact person

1.1Drift Tube Linac CEA,CERN, lpsc 1.1.1 DTL design t Jun-07: Intermediate repor CEA -Bernaudin

1.1.2 Development of critical DTL components Jan-07: Intermediate report Jan-07: Prototy pe ready RAL-Plostinar 1.1.3 DTL beam dynamics design Jun-08: Intermediate report

1.1.4 Optimised DTL design Dec-08: Final report 1.2 H-mode Drift Tube Linac

1.2.1 CH model cav ity construction, tests Dec-05: Intermediate report Mailed 11sep06

IAP-FR RAtzinger

1.2.2 Prototype design, construction, tests Dec-06: Prototype ready IAP-FR RAtzinger

1.2.3 H-DTL beam dynamics Jun-05: Design report 1.2.4 H-DTL design finished Dec-08: Final report

1.3 Side Coupled Linac 1.3.1 RF cold model prototy pe design, test Dec-07: Final report Cern lpsc

1.4 Cell Coupled Dri ft Tube Linac 1.4.1 Pre-prototype testing Jun-05: Intermediate report Delayed OCT06 CERn CEA LPSC

1.4.2 Prototype design, construction, test Jun-06: Prototype ready Dec-06: Design report Delayed dec06 1.4.3 CCDTL design finished Jun-08: Final report

1.5 Comparative assessment of NC structures Dec-08: Final repor WP3: SUPERCONDUCTING STRUCTURES

2.1 Elliptical cavities 2.1.1 Cav ity A vertical tests Dec-04: Intermediate report INFN-pierini

2.1.2 Tuner design construction & test Dec-05: Intermediate report INFN-pierini 2.1.3 Cavity A assembly

2.1.4 Cav ity A ready in CRYOLAB Mar-07: Cavity A ready INFN-pierini 2.1.5 RF Coupler design and test CEA Chel

2.1.6 Design, construction assembly cav ity B CEA Chel

Page 5: CSC, 13.9.2006 1 Status of HIPPI – September 2006 Maurizio Vretenar Alessandra Lombardi.

5 CSC, 13.9.2006

Dissemination & ReportsDissemination & Reports

(info from Alessandra):

- 17 CONF papers (EPAC and LINAC Conferences in 2006).

- 7 CARE Notes (some HIPPI-DOC have been promoted to CARE Notes).

- 2 CARE Reports

- 1 HIPPI-DOCument

2nd Quarterly Report 2006 completed (6.9.06).

Page 6: CSC, 13.9.2006 1 Status of HIPPI – September 2006 Maurizio Vretenar Alessandra Lombardi.

6 CSC, 13.9.2006

HIPPI06 Meeting in JHIPPI06 Meeting in Jüülichlich

- JRA Meeting on September 27th – 29th in Julich (FZJ, financial contribution from the Direction will cover banquet and internal transportation).

- Expected 30 – 40 participants from all contributing institutes + 1 or 2 external.

- Confirmed participation of the 3 members of the ESAC: J. Stovall (LANL-SNS), Y. Yamazaki (KEK-JPARC), A. Pisent (LNL).

- Some modifications to the structure of the meeting:

4 sessions of 3 hours for each of the 4 Work Packages (programme under responsibility of the WP Coordinator)

1 general session covering topics between WP’s (resp. Coordinator)

2 talks on the status of the linac projects covered by HIPPI (GSI and CERN).

More time for the ESAC

Page 7: CSC, 13.9.2006 1 Status of HIPPI – September 2006 Maurizio Vretenar Alessandra Lombardi.

7 CSC, 13.9.2006

HIPPI06 Preliminary ProgrammeHIPPI06 Preliminary ProgrammeWednesday 27, September, morning

9h00-9h30 9h30-12h00 12h00-12h30

Welcoming address and Introduction

WORK PACKAGE 4 (Chopper) General: Review of HIPPI Prototypes and

alternative designs

R. Tölle, M. Vretenar A. Lombardi (conv.)

Wednesday 27, September, afternoon

14h00-14h30 14h30-15h00 15h00-18h00

General: Status of GSI linac design Status of CERN linac design

WORK PACKAGE 2 (NC Structures)

J.M. De Conto (conv.)

Thursday 28, September, morning

8h30-12h00 12h00-12h30

WORK PACKAGE 3 (SC RF structures) General: Comparison NC/SC designs (>90 MeV)

S. Chel (conv.)

Thursday 28, September, afternoon

14h00-17h00 17h00-19h00 17h00-19h00

WORK PACKAGE 5 (Beam Dynamics) First meeting of the ESAC Visit of FZJ accelerator laboratory (in parallel)

I. Hofmann (conv.)

Thursday 28, September, evening: Social event (t.b.c.)

Friday 29, September, morning

9h00-11h00 9h00-11h00 11h00-12h00

HIPPI administrative meeting (deliverables, planning, budget) Second meeting of the ESAC (in parallel) Plenary meeting, ESAC preliminary assessment

Programme will be finalised on Sept. 15th.

Slides on the web (for the ESAC) one week before the meeting.

Page 8: CSC, 13.9.2006 1 Status of HIPPI – September 2006 Maurizio Vretenar Alessandra Lombardi.

8 CSC, 13.9.2006

Status of HIPPI – Technical InfoStatus of HIPPI – Technical Info

- A negative point for the coordination between EU project: GSI has chosen for the FAIR Linac the frequency of 324 MHz (Toshiba klystrons), as RAL did already a year ago. Arguments: Toshiba is becoming leader on the market (JPARC, China) + have a common frequency with a possible UNILAC upgrade (324=3*108).

- CERN remains alone in the choice of 352 MHz for Linac4, imposed by the available LEP klystrons (8 MEUR value for the project) and other RF equipment and by the frequency of the IPHI RFQ.

- A common frequency would have allowed to gain more weight towards the klystron manufacturers, via competition between Thales and Toshiba.

- The choice of 324 MHz gives a clear preference to a non-EU company (Toshiba) and could definitely cut out of the market Thales.

Page 9: CSC, 13.9.2006 1 Status of HIPPI – September 2006 Maurizio Vretenar Alessandra Lombardi.

9 CSC, 13.9.2006

Status of Linac4 & GSI FAIR linacStatus of Linac4 & GSI FAIR linac

- Linac4 included in the Medium Term Plan submitted to the Council at the end of the year. Upon demand by R. Aymar, minimum funding in 2007 (1.3 MCHF, but 6 additional posts). Real funding from 2008, first injections in PSB from 2011.

- Technical Design Report in preparation (draft 15.10.06), big step forward in the machine design.

- New options under consideration: single frequency (352 MHz only), new position in an extension of the Linac2 tunnel.

- GSI will start ordering a klystron prototype already in 2006. The accelerating cavities (CH) have modified by adding a coupling cell that allows reducing splitting from klystrons.

Page 10: CSC, 13.9.2006 1 Status of HIPPI – September 2006 Maurizio Vretenar Alessandra Lombardi.

10 CSC, 13.9.2006

Highlights WP 2 – Normal Highlights WP 2 – Normal Conducting StructuresConducting Structures

The Russian ISTC DTL Prototype is late by 5 months (and some technical points are not clear yet): will be delivered to CERN at best in August 2007, quite late for the decision on Linac4 DTL.

New layout (with coupling cell) of the CH cavities made at Frankfurt for GSI

One cell of cold model of SCL for Linac4 finally made at LPSC – activity about 1 year late, concerns for Linac4.

CCDTL prototype (Linac4) finally under high power RF testing at CERN (1yr late).

CCDTL prototype made in Russia waiting for some brazed parts (priority to LHC).

Page 11: CSC, 13.9.2006 1 Status of HIPPI – September 2006 Maurizio Vretenar Alessandra Lombardi.

11 CSC, 13.9.2006

Highlights WP 3 – Highlights WP 3 – Superconducting StructuresSuperconducting Structures

Progress in the design of spoke cavities + definition of a spoke layout in competition with NC designs.

Preparation of 704 MHz test stand in Saclay:-klystron (CPI) on schedule, should be delivered before end 2006.-HV power supply to be assembled before end of 2006

Page 12: CSC, 13.9.2006 1 Status of HIPPI – September 2006 Maurizio Vretenar Alessandra Lombardi.

12 CSC, 13.9.2006

Highlights WP 4 – Beam Highlights WP 4 – Beam choppingchopping

The CERN chopper line as it will be mounted on the IPHI RFQ support at Saclay.

Chopper tests at Saclay:

The persisting delays in the IPHI RFQ (machining+brazing) would put at risk the HIPPI chopper tests: delivery of the RFQ at CERN foreseen only at end 2008.

A temporary set-up has been defined to allow testing of CERN chopper at Saclay in 2nd half 2008.

Page 13: CSC, 13.9.2006 1 Status of HIPPI – September 2006 Maurizio Vretenar Alessandra Lombardi.

13 CSC, 13.9.2006

WP 4 – Beam choppingWP 4 – Beam chopping

Vacuum test of CERN chopper made (2 E-9 mbar reached last Monday).Driver prototype should arrive mid-September and power tests can start soon.

Page 14: CSC, 13.9.2006 1 Status of HIPPI – September 2006 Maurizio Vretenar Alessandra Lombardi.

14 CSC, 13.9.2006

WP 5 – Beam dynamicsWP 5 – Beam dynamics

The first bloc of the UNILAC beam dynamics experiment planned for HIPPI was successfully conducted end of May.

The experimental data are in the process of being compared with different simulation codes (Parmila, Dynamion and Path).

Page 15: CSC, 13.9.2006 1 Status of HIPPI – September 2006 Maurizio Vretenar Alessandra Lombardi.

15 CSC, 13.9.2006

HIPPI Detailed PlanningHIPPI Detailed Planning

ID Task Name

1 WP2: NORMAL CONDUCTING STRUCTURES

2 2.1 Drift Tube Linac

3 2.1.1 DTL design

6 2.1.5 DTL coupler prototype construction and testing

7 2.1.4 DTL beam dynamics design

8 2.2 H-mode Drift Tube Linac

10 2.2.2 RF cold model design & construction

11 2.2.3 RF model construction

13 2.2.5 CH model cavity tests

15 2.2.7 CH-prototype construction, tests

17 2.3 Side Coupled Linac

18 2.3.1 RF model RF design

19 2.3.2 RF model mechanical design

20 2.3.4 RF model construction

24 2.4 Cell Coupled Drift Tube Linac

26 2.4.2 Pre-prototype high-power RF tests

28 2.4.4 Revision of design after prototype testing

30 WP3: SUPERCONDUCTING STRUCTURES

31 3.1 ELLIPTICAL CAVITIES

35 3.1.4 Tuner construction

38 3.1.6 Construction cavity B

40 3.1.7 Power coupler design & engineering

42 3.1.8 RF source order & construction

43 3.1.10 Modulator preparation for 700 MHz test stand

46 3.2 SPOKE CAVITIES

51 3.2.5 Construction of coupler prototype

55 3.2.8 Final design of 352 MHz multi-gap prototype

56 3.2.10 Manufacturing of 352MHz multi-gap prototype

58 3.3 CH RESONATOR

59 3.3.1 Design of tuning system

CEA,CERN,LPSC

CEA,LPSC

RAL

IAP-FU

IAP-FU

IAP-FU

LPSC,CERN

LPSC

LPSC

CERN,LPSC,CEA

CERN

INFN-MI

CEA

CEA

CEA

CEA

IN2P3-Orsay

FZJ,IN2P3-Orsay

FZJ

IAP-FU

01 02 03 04 05 06 07 08 09 10 11 12 01 02 03 04 05 06 07 08 09 102006 2007

Page 16: CSC, 13.9.2006 1 Status of HIPPI – September 2006 Maurizio Vretenar Alessandra Lombardi.

16 CSC, 13.9.2006

Planning - 2Planning - 2

ID Task Name

62 WP4: CHOPPING

63 4.1 CHOPPER STRUCTURE A

66 4.1.3 Driver construction, testing

69 4.1.6 Prototype testing w/o beam

70 4.2 CHOPPER LINE

72 4.2.2 Dump construction

74 4.3 CHOPPER STRUCTURE B

76 4.3.2 Prototype design

78 WP5: BEAM DYNAMICS

79 5.1 Code development

80 5.1.1 3D space charge routines development, testing

82 5.1.3 Neutralization and ECR source modelization study

83 5.1.4 Improvement, modell ing high current

84 5.1.5 Code preparation for 3 MeV test stand

85 5.1.6 Code preparation and analysis for SC l inacs

86 5.1.7 Code comparison and benchmarking

88 5.2 Experiment at UNILAC

89 5.2.1 Preparation, simulations

92 5.3 Diagnostics and collimation

94 5.3.2 Profi le measurement testing

96 5.3.4 Non-interceptive bunch measurement const., testing

98 5.3.9 Test and improvement of halo monitor

99 5.3.6 On-line transmission control

100 5.3.7 Beam profi le monitor design

CERN

CERN,CEA,LPSC

RAL

RAL

CEA

GSI

CERN

FZJ

GSI,RAL,IAP-FU,CEA,CERN,LPSC

GSI

GSI

GSI

GSI

FZJ

01 02 03 04 05 06 07 08 09 10 11 12 01 02 03 04 05 06 07 08 09 102006 2007