L.Mandelli CSN1 Settembre 2005 1
Stato Generale di Atlas
• Stato dei Toroidi
• Stato dei sottosistemi( dettagli e richiete finanziarie INFN
http://agenda.cern.ch/fullAgenda.php?ida=a054647 )
• Schedule
• Le Finanze
• Conclusioni
L.Mandelli CSN1 Settembre 2005 2
August ‘05
L.Mandelli CSN1 Settembre 2005 3
26 Oct :Barrel Calo at IP
22 Sept (?) :jacks released BT accessible !
remove top and central platforms
install mu-rail where possible
install cryo services through the BT. Now 5/8 cryorings are in position and 3 sections connected
install BMS mu chambers
install upper HS
Vacuum pumping in DecemberCooling at XMas
Full Test in February-March (it was end January)
1 Milan phys/tech always there
Recall:
The cold mass production in industry stopped. The contract with the was company cancelled and the work moved to CERN one year ago.ECT-A confirmed to be the first one to go to the pit
• All 16 coils and keystone boxes ready for assembly
• Assembly of ECT-A has started in July, cold mass is ready now.• Assembly in cryostat. End January 06.
• Vacuum tested in H191 in Feb. 06.
• Cooled down at 80k in B180•• Moved to the pit and Cooled down at 4K in May 06 (was March 06
ECT-C will followMajor problems solved
End Cap Toroids
L.Mandelli CSN1 Settembre 2005 4
L.Mandelli CSN1 Settembre 2005 5
ECT-A in B191
L.Mandelli CSN1 Settembre 2005 6
Barrel
3 layers MDTinner BImedium BMouter BO
3 layers of RPC2 coupled to the middle MDT1 coupled to the outer MDT
Each layer has Small and Large Chambers +....
MDT Chambers: Status
72% Integrate 69% testedL.Mandelli CSN1 Settembre 2005 7
L.Mandelli CSN1 Settembre 2005 8
RPC: Production
0
250
500
750
1000
1250
feb-02
mag-02
ago-02
nov-02
feb-03
mag-03
ago-03
nov-03
feb-04
mag-04
ago-04
nov-04
feb-05
mag-05
ago-05
nov-05
unità assemblatepiano di prod. feb. 05
0
250
500
750
1000
1250
feb-02
mag-02
ago-02
nov-02
feb-03
mag-03
ago-03
nov-03
feb-04
mag-04
ago-04
nov-04
feb-05
mag-05
ago-05
nov-05
unità assemblatepiano di prod. feb. 05
•Recent delamination problem on BOS #3 support panel (Protvino) solved
•Detailed plan to complete production in Lecce in 2005
• BOL tests will follow in Rm2•Measure of leakage currents started in H8•Bologna group very active in the game
55.636.588.1100100%8070178280298Done144192202280298LayoutspecialBOLBOSBMSBMLType
55.636.588.1100100%8070178280298Done144192202280298LayoutspecialBOLBOSBMSBMLType
CR test MDT+RPC
Integrate MDT with CS-RPC
RPC plane assembly Mounting of cable stops (add. GND)
MDT preparation:
Mount B-sensorsGlue alignment platforms (some chambers only)
Mount CSM
MDT pre-test:Leak testNoise test
Integrate RPC with
Common Sup.
RPC pre-test
Sag-adjust MDT onrotator frame
LV1 trig.
cabling
Adjust relative positionMDT versus CS
integration
RPC
LV1
Assembly, Integration and test in BB5 (MDT+RPC+Trigger)It is a small industry ( 25 people)! Now better organized thanks to a coherent effort of all the community
L.Mandelli CSN1 Settembre 2005 9
L.Mandelli CSN1 Settembre 2005 10
Assembly status in BB5(2.9.2005)
Totalstations
RPC planesassembled
Assem.stations
CRtest
168
167
51
6
84
392
80
84
15
11
6
25
6116195
Installed pit
BOL 96 3
BMS/F 84 36
BML 94 6
BOS/F/G
106 10
Tot 380 55
51% stations assembled
ok !
30%51%•
L.Mandelli CSN1 Settembre 2005 11
Preliminary updated installation plan (2005)
MDT/RPC muon station installation V7.03 (T0 =Augu 30th + 6 weeks)
0
10
20
30
40
50
60
70
80
90
1-Jan-05 2-Mar-05 2-May-05 2-Jul-05 31-Aug-05 31-Oct-05 31-Dec-05
Cha
mbe
rs
BMSBMLBOSFGBOL
All BM
78/106 BOS
48/96 BOL
18/94 BML
All BM
78/106 BOS
48/96 BOL
18/94 BML
Challenge: 8 stations/w needed. Maximum of 5 reached
L.Mandelli CSN1 Settembre 2005 12
Next 2 months : BMS chambers
BMS assembly on the toroid
Few mm tolerance
weigh like a car
Goal 2.5 stations/day
L.Mandelli CSN1 Settembre 2005 13
Item Number Group Production
Phi cables 6100 Roma1 70%
ETA cables 33000 Roma1 25%
Low_high_Pt_cables
2500 Roma1 70%
Splitters 832 boxes / 11700 boards
Roma1 100%
CM ASICs 3328 Roma1 100%
LowPt PAD processors
416 boxes / 2500 boards
Roma1 10%- Test iniziale a Bo; finale al CERN
HighPt PAD processors
416 boxes / 2500 boards
Roma1 10%
LV1 On Detector
L.Mandelli CSN1 Settembre 2005 14
Item Number Group Production
LV system 34 crates/157 modules Roma1 <5%
Optical links 416 TX + 208 RX Napoli 100%
Optical fibres and patch panel
416 fibres / 64 bundles / 128 patch panels
Napoli/CERN
5%
RX/Sector Logic 64 boards Roma1 -
MUCTPI Interfaces
64 boards Roma1 -
RODs 32 boards Napoli -
RODbus 32 backplanes Napoli 100%
VME crates / Crate Controllers
32 systems Roma1 <5%
TTC system 2 crates / 6 boards CERN 100%
CANbus Control 4PCs / 64 CAN Roma1 -
LV cable 90 km Roma1 90%
off
detector
L.Mandelli CSN1 Settembre 2005 15
L.Mandelli CSN1 Settembre 2005 16
Mu spectrometer EC
3 MDT Wheels1 CSC wheel1 TGC Wheels
staged
3 TGC wheels
L.Mandelli CSN1 Settembre 2005 17
EC- Precision chambers
CSC completed from long time
MDT almost construction completed
1 MDT Large sector fully assembled and chambers and services under test
All mechanical parts of the 64 sectors are either done or being manufactured (Novosibirsk)
L.Mandelli CSN1 Settembre 2005 18
EC Trigger Chambers
TGC trigger chamber production is 98% completed (all big-wheels available)
All wheels divided in sectors
Sectors will be fully assembled with services and tested in B180. than lowered in the pit
1 TGC sector fully assembled aligned and tested
All mechanical parts for TGC1;2 manufacturedMechanical parts for TGC3 being manufactured
L.Mandelli CSN1 Settembre 2005 19
Barrel Calorimeters installation completed on 10/12/2004
Status:• Mechanics:
• installation OK. Geometry within the envelope• movement of barrel tested OK • installation of services proceding ( cryo, power etc)
• Tiles Electronics:• Drawers: some failures (10%); being fixed• LV PS: still on critical path but the first 20 units being delivered this
week• HV, work in progress, still some problem of stability (readout?).• RODs: units are almost ready, programming still in progress
LAr ElectronicsFEB production at full speed. All production almost finishedbut test ( digital and analog) very slow. 3 crates in the pit.LV great improvement. In production. 8/32 available (4 at CERN)HV improving but not stable enough for Atlas yet. Sw stableBE installed ! Great!
L.Mandelli CSN1 Settembre 2005 20
Ready to roll in: 26th October
L.Mandelli CSN1 Settembre 2005 21
EC calorimeters
EC-C: warm. Ready to be transported to the pit 280t!
EC-A : Middle June: start cool down Middle Aug : start testsMiddle Sept: start warm up
EM :Detector status at cold o.k. similar to EC-C (preliminary)But more HV problems than hoped and a bit more than on ECC.
HEC : Status ok. No HV dead regions. Bad channels at ‰level
FC : 1 problem with 1 HV line. 25% of channels of 1 quadrant (uniform spread lost)
Short on 1 sides
short and not nominal
Not nominal (>25%)
Shorts on both sides
L.Mandelli CSN1 Settembre 2005 22
L.Mandelli CSN1 Settembre 2005 23
Inner Detector (ID)The Inner Detector (ID): four sub-systems:
Transition Radiation Tracker (TRT)(4 105 channels)
Silicon Tracker (SCT)4 cylinders + 9*2 wheels(6 106 channels)
Pixels 3 cylinders + 3*2 wheels(80 106 channels)
Common ID
L.Mandelli CSN1 Settembre 2005 24
All four barrel cylinders are complete and at CERN. Tested The integration into the cylindrical support structure has started. Integration with TRT in Dec
SCT Barrel
Outermost ATLAS SCT barrel cylinder before insertion into the support structure
L.Mandelli CSN1 Settembre 2005 25
SCT endcapAll SCT disks for the first end-cap (9/9) are finished (Liverpool), and they are well-advanced 3/9 for the second one (Nikhef)
The recovery from a failure of the end-cap LMTs (low mass tapes for electricalservices) is proceeding according to the plans (requiring fabrication of new LMTs)
SCT disk Support cylinder for SCT end-cap disks
L.Mandelli CSN1 Settembre 2005 26
Pixel Barrel
Sensor production almostfinished (3 Layers)
Total deliveries
0200400600800
1000120014001600
01/0
2/20
0401
/04/
2004
01/0
6/20
0401
/08/
2004
01/1
0/20
0401
/12/
2004
01/0
2/20
0501
/04/
2005
01/0
6/20
0501
/08/
2005
data
mo
du
lideliveredvirginall accepted
Module production stable 20*2/w.Acceptance ~90%.1744 needed for Atlas2200 produced Feb 20062500 produced April 2006
Flexproduction and test also ok
L.Mandelli CSN1 Settembre 2005 27
Staves
Loaded Staves
0
20
40
60
80
100
120
01/08/04 09/11/04 17/02/05 28/05/05 05/09/05 14/12/05 24/03/06
Date
No.
Loaded Staves
Original half-shell need
Production delayed by delamination of barrel support staves. Solved.
44 staves/112 were completed
But now serious problem with corrosion of the cooling lines( see Chiara)
Critical ID piping : 6 weeks delayBut not only detectors! Also ID services are a challenge! Layout of the cooling lines were underestimated. Big effort from TC.
Plan to finish for the 23th of October (critical last 2 sectors 1 and 9)
L.Mandelli CSN1 Settembre 2005 28
L.Mandelli CSN1 Settembre 2005 29
ATLAS TDAQ system
Muon
ROD ROD ROD
LVL1
LVL2
Event builder network
Storage: ~ 300 MB/s
ROBROB ROBROB ROBROB
Calo Inner
PipelineMemories
ReadoutDrivers
ReadoutBuffers~1600
High-Level Trigger
LEVEL-1 TRIGGER• Hardware-Based• Coarse granularity from calorimeter & muon systems
LEVEL-2 TRIGGER• Regions-of-Interest “seeds”• Full granularity for all subdetector systems
• Fast Rejection “steering”
EVENT FILTER • Possibly “seeded” by Level 2 • Full event access• Algorithms inherited by offline
RoI
EF farm~1000 CPUs
1 selected event
every millionTDAQ ≅Rates
40 MHz
~75 kHz
~2 kHz
~200 Hz
~2 ms
~10 ms
~ 1 s
Latency
EF
LVL2farm
L.Mandelli CSN1 Settembre 2005 30
• Functionality and system dimension studies– Pre-series system installed in the pit. Equivalent to Mod-0
used for integration, functionality studies and commissioning. 10% data flow reduced EF farm
– Large Scale Tests su cluster di PC esistenti (Canada, CERN)
• Developments of DAQ tools (CERN &INFN)– ROD Crate DAQ to control the configuration.– Monitoring System(GNAM) based on plug-in modules– Event Filter dataflow development and DAQ interfaces
– Developments of selection algorithms– Livello-1 Mu Barrel Simulation– LVL2 mu and silicon detectors (Pixels+SCT). Tiles– EF for mu, standalone and combined also with inner
detector• Cosmic run preparation
– Development of algorithms dedicated to CR
L.Mandelli CSN1 Settembre 2005 31
Large ScaleTest Results• 1 controller + 1 example application, each on separate nodes up
to 700 nodes, for larger partitions the processes were distributed over all 700 nodes
• Very good behaviour for state transitions• For > 4000 processes• Setup: 16 minutes
One State transition: 7sTransition Time
results_100_2000_set_A
0100200300400500600700800900
1000
0 500 1000 1500 2000Number Local Controllers
Seco
nds
BootSetup
Transition Time results_100_2000_set_A
05
101520253035404550
0 500 1000 1500 2000Number of Local Controllers
Seco
nds
Configure PlusStart (4 transitions)Start (2 transitions)
Stop (5 transitions)
stop and unload (7transitions)
700 nodes reached
L.Mandelli CSN1 Settembre 2005 32
Ex: EF algoritmMuon Vertical SliceEx: EF algoritmMuon Vertical Slice: TrigMoore @ EF: TrigMoore @ EF
σpT/pT~3%(MuId)
σφ=0.0025(MuId)
ση=0.0018(MuId)
ηm
uFas
t
η TrigMoore
φm
uFas
t
φ TrigMoore
Reconstruction with TrigMoorein the RoIs selected by muFast
2000 single µ, pT=100 GeV/c, |η|<3.2
L.Mandelli CSN1 Settembre 2005 33
Schedule.Schedule 7.03 is clearly obsolete. New schedule in preparation to be discussed at the next Friday EB and approved at next Atlas CB ( main emphasis on next 6 months)
Expected sequences:
Barrel Calorimeters central position 26 Oct 05EC-C Calorimeters ( EB & EC ) Nov-JanEC-C “Interaction point” Middle Feb 06EC-A Installation Feb-May 06
Barrel mu stations installation Oct05-April06
Magnet (BT+solenoid) Feb-April
ID Services installation (many unknown) Oct05-May06ID Barrel insertion End MayID EC A&C insertion Late summerForward regions will follow (ECT, MU etc)
Pixel insertion will be delayed as much as possible
L.Mandelli CSN1 Settembre 2005 34
NB: members have grown from162/215/ to 185/245 ( +14%) Bo groups
(1) Consumo includes:623kE MOF-A264kE MOF-B
(2) CA includes the CtC part of the planned 4MChF
248kE CtC A366kE CtC-B
and a request (obviously flexible) of the 50% of the remaining CtC
867kE 50% compl. CtCA
Atlas Finance :• No cash problem forseen in 05 thanks also to CERN help• Canada will pay the full CtC contribution2006 INFN request (modules)
2006 2005
MI 297 275ME 2955 3093Consumo 1441 (1) 891Trasporti 38 86Affitti 8.5 8.5Inventario 276 380Costruzione Apparati
4406 (2) 5080
Totale 9421 9815
L.Mandelli CSN1 Settembre 2005 35
PhysicsMain event was the Rome Atlas Physics workshopOccasion for the whole collaboration to review the status of the physics and detector performance studies:
The preparation effort was large:Full simulation and reconstruction of 8M events in two months using the Grid tools, events made available to the community in the form of AOD’s
The response of the community was exceptional :450 participants; 100 talks.
Next steps
Finalize analyses in for the Autumn physics week
Prepare for DC3 as the commissioning of the Atlas SW & Event Data Model
L.Mandelli CSN1 Settembre 2005 36
Main conclusions (GP)
User-driven production on the grid did deliver data, but required toomuch human intervention, need evolution in that sector
The transition G3/G4 is now accomplished, should continue validation, using CTB data
ATLAS framework usable for analyses, now need to address performance issues and evolving analysis tools according to feedbackreceived
Next steps
Finalize Analyses of the Rome sample (Autumn Atlas Physics week )Prepare for DC3 as a real commissioning test of SW&CItalian partecipation very good. Now we need to move the
community from MC data analyses to real analyses. Ideas of tutorials from computing and analyses tools to “workshops” were to merge internal existing experience on selected items to favorite the concentration of forces on relevants topics
L.Mandelli CSN1 Settembre 2005 37
Require Mwwithin 10 GeV of nominal W mass S/B = 1.77
Top mass (GeV)
m(t)
Ex: Top study with 1 week data!Selection cuts: ETmiss > 20 GeV, 1 lep Pt > 20 GeV, 4 jets Pt > 20 GeV
No trigger selection efficiency taken into account yet
Preliminary
Measured top mass 160.0 ± 1.0 GeV , stat error on xs: 8.3%
I progressi compiuti nell’ ultimo anno sono notevolissimi :Il toroide esiste ed i rivelatori sono o costruti o in fase molto avanzata. Inizia il commissioning
I problemi sono (quasi) quotidiani, ma la forza e capacità dei reazione della collaborazione sono sempre stati eccezionali.
La componente italiana come impegno, qualità e risultati non ha nulla da invidiare a nessuno. Inoltre si è rafforzata con l’ingresso del gruppo di Bologna.
Ad oggi c’è un ritardo di circa 2 mesi. La capacità di seguire la schedula dipenderà da moltissimi fattori in primis dalla capacità di modulazione e sincronizzazione delle operazioni di assemblaggio (devil is in the details)
Oggi il problema più acuto son i pixel, ma non sono uno show stopperSono ancora convinto che nel 2007 attraccheremo.
Quando? Chiedete alla Sibilla Cumana!
Conclusioni
L.Mandelli CSN1 Settembre 2005 38
L.Mandelli CSN1 Settembre 2005 39
Spares
L.Mandelli CSN1 Settembre 2005 40
Status of gas volume production
Certificazione volumi di gas
0
500
1000
1500
2000
2500
3000
3500
4000
9/30/2002 4/1/2003 10/1/2003 4/1/2004 10/1/2004 4/2/2005 10/2/2005
Volu
mi d
i gas
acc
etta
ti (e
sclu
si g
li sp
are)
Layout: 3704
Status :• 94.1% done and
certified
Status :• 94.1% done and
certified
Status :• 90.4% Eta done• 90.4% Phi done
– panels with holes all done
– Only BOL strip panels left
Status :• 90.4% Eta done• 90.4% Phi done
– panels with holes all done
– Only BOL strip panels left
Status of RO Strip panel productionProduzione pannelli di readout
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
4/1/2001 10/26/2001 5/22/2002 12/16/2002 7/12/2003 2/5/2004 8/31/2004 3/27/2005 10/21/2005
Stan
dard
0
100
200
300
400
500
600
700
800
900
Spec
iali
StandardTotale_Standard (8016)SpecialiTotale_Speciali (528)
L.Mandelli CSN1 Settembre 2005 41
L.Mandelli CSN1 Settembre 2005 42
Piano di produzione RPC (14.9.05)
31-g
en-0
5
07-fe
b-05
14-fe
b-05
21-fe
b-05
28-fe
b-05
07-m
ar-0
5
14-m
ar-0
5
21-m
ar-0
5
28-m
ar-0
5
04-a
pr-0
5
11-a
pr-0
5
18-a
pr-0
5
25-a
pr-0
5
02-m
ag-0
5
09-m
ag-0
5
16-m
ag-0
5
23-m
ag-0
5
30-m
ag-0
5
06-g
iu-0
5
13-g
iu-0
5
20-g
iu-0
5
27-g
iu-0
5
04-lu
g-05
11-lu
g-05
18-lu
g-05
25-lu
g-05
01-a
go-0
5
08-a
go-0
5
15-a
go-0
5
22-a
go-0
5
29-a
go-0
5
05-s
et-0
5
12-s
et-0
5
19-s
et-0
5
26-s
et-0
5
03-o
tt-05
10-o
tt-05
17-o
tt-05
24-o
tt-05
31-o
tt-05
07-n
ov-0
5
14-n
ov-0
5
21-n
ov-0
5
28-n
ov-0
5
05-d
ic-0
5
12-d
ic-0
5
19-d
ic-0
5
26-d
ic-0
5
week # 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52
work days N 5 5 5 5 5 5 5 4 3 5 5 5 4 5 5 5 5 4 5 5 5 5 5 5 5 5 5 5 4 4 5 5 5 5 5 5 5 5 5 4 5 5 5 5 4 5 4 0manpower FAI 30 1 1 1 1 1 2 2 2 2 2 2 2 2 4 4 4 2 2 4 4 4 4 2 2 4 4 4 4 0 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 2 2 0manpower art. 15 10 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0
gas volumes delivery from GT 32 32readout panels delivery from RM2 180 20 128 32gas volumes delivery from GT 63 43 12 8
readout panels delivery from RM2 559 41 144 48 7 184 2 96 5 32procurementproduction 170 1 6 21 43 49 20 30
gas volumes delivery from GT 143 13 46 42 17 20readout panels delivery from RM2 456 96 104 8 82 16 4 96 50
local production 6 6delivery from IHEP 200 12 66 122procurementproduction 192 10 2 9 16 20 20 20 20 20 20 20 15
support panel #2 delivery from IHEP 242 242gas volumes delivery from GT 731 11 43 119 263 45 87 23 36 36 36 32
readout panels delivery from RM2 1536 72 80 88 64 192 101 11 120 96 96 96 96 96 96 96 56 80
rest of BML 11 2 5 test NA 4 test RM2BML-G 16 16 test RM2rest of BMS 14 4 test NA 3 test LE 2 test LE 1 test LE 4 test RM212E3h + 4Dco 16 4 test LE 2 10 test LEspecial units S2 72 6 20 9 test LE 13 test LE 24 test RM2special units S3 24 24 test RM2repair BOS-B 92 8 5 quick test 32 21 20 6 quick test LE39 BOS-B 39 1 12 5 test LE 4 17 test LE7C+2D*+4E 32 1 2 4 12 test LE 6 test LE 7 test LE4A1h + 12B1h 16 4 4 test LE 4 test LE 4 test LEBOL-B 97 2 6 12 2 5 5 14 14 14 13 10BOL-D 73 2 1 7 1 11 8 14 12 14 3BOL-E 22 5 3 7 1 6
##
units to be assembled 8 gas vol. to be deliv. 37 OK - done! 4units to replace s.p.#1 24 readout panels to be del. 96 delayed item 10supp. panel to be prod. 16 supp. panels to be deliv. 56
BMS
BOS
legenda
BOL
ASSEMBLY
BML
BOL
BOS
Manpower
support panel #1
support panel #1
support panel #3
PROCUREMENT
BMS
BML
New schedule with a reduced production/test rate End of the BOL production: 1 December ‘05End of the RPC production (special units): End of December ‘05
L.Mandelli CSN1 Settembre 2005 43
RPC readout and LVL1 trigger slice
ON-detector (Roma)– 832 front-end receiver and fan out boxes (splitters)– 416 Low Pt and 416 High Pt Trigger Processors(pad)
OFF-detector (Napoli/Roma)– 64 Sector Logic/RX modules + 64 Interface to MUCTPI boards– 32 RODs + 32 ROD backplanes– Services,TTC system,CANbus based initialization system,LV system
Un gruppo di Bologna (A.Zoccoli) si e’ aggiunto all’attivita’ di LVL1Un gruppo di Bologna (A.Zoccoli) si e’ aggiunto all’attivita’ di LVL1
L.Mandelli CSN1 Settembre 2005 44
“Standard conditions”
Critical muon station readinessToday key issues:
• BOL chambers construction in Lecce/Rome
• BML initial production noise quality (RPC), how much rework?
• BOS new delamination of Al panels (repair solution found)
• Keep level of manpower at BB5 as today for the next 3-4 months
The new organization is in place and it seems this time to be ok!
L.Mandelli CSN1 Settembre 2005 45
L.Mandelli CSN1 Settembre 2005 46
Installazioni stazioni a muoni previste per Dic ‘05
8
USA
76
5
43
2
10
11
1
16
1514
13
12
9
Installate
Da installareInstallate
Da installare
US
L.Mandelli CSN1 Settembre 2005 47
Tavola LV1LVL1 Barrel System
Item Number Group ProductionPhi cables 6100 Roma1 70%
CM ASICs 3328 Roma1 100%
Optical fibres and patch panels 416 fibres / 64 bundles / 128 patch panels
Napoli/CERN 5%
LV cable 90 km Roma1 90%
ETA cables 33000 Roma1 25%
Low_high_Pt_cables 2500 Roma1 70%
Splitters 832 boxes / 11700 boards Roma1 100%
LowPt PAD processors 416 boxes / 2500 boards Roma1 10%
HighPt PAD processors 416 boxes / 2500 boards Roma1 10%
Optical links 416 TX + 208 RX Napoli 100%
MUCTPI Interfaces 64 boards Roma1 -
RODbus 32 backplanes Napoli 100%
VME crates / Crate Controllers 32 systems Roma1 <5%
TTC system 2 crates / 6 boards CERN 100%
CANbus Control 4PCs / 64 CAN Roma1 -
RX/Sector Logic 64 boards Roma1 -
RODs 32 boards Napoli -
LV system 34 crates/157 modules Roma1 <5%
L.Mandelli CSN1 Settembre 2005 48
L.Mandelli CSN1 Settembre 2005 49
ECA cooling down
L.Mandelli CSN1 Settembre 2005 50
EM Barrel BE Commissioning• CPU, ROD, TM, TBM and SPAC
Masters modules installed in all 8 EMB crates.
• All EMB crates were tested individually:
• Some RODs and TMs with errors:they have been replaced.
• All EMB modules should work!
• This represents achievement of a MAJOR milestone!!!
L.Mandelli CSN1 Settembre 2005 51
EMEC-C Short SummaryFoundjust beforeemptying !
15 sectors10 spare lines
Red : 1 sideBlack : both sidesShort between2 sectors
None problemappeared duringwarming up
L.Mandelli CSN1 Settembre 2005 52
HEC A – CommissioningHV tests (S. Chekulaev)
new
new
newnew
new
new
new
new
newnew
new
new
HEC1 A HEC2 A
new
Current
Current
L.Mandelli CSN1 Settembre 2005 53
Disk Rings
Endplate
Endcone
Disk Frame
Barrel Frame
Disk Ring Mounts
Sectors
Barrel ShellsStaves
“PIXEL DETECTOR”
PIXEL DETECTOR
Pixel Detector Package vieneassemblato sull’ITT ed e’ formato da:• Beam Pipe• Barrel Frame• Half Shells (Layer 1 and Layer 2) • B-layer half shells• Disk Sectors
L.Mandelli CSN1 Settembre 2005 54
Cosmic in TRT
L.Mandelli CSN1 Settembre 2005 55
Next 2 months : HS archesThe top part of the arches will be pre-assembled into 3 large sections, and equipped with platforms and cable trays, already on surface.
Already installed.
L.Mandelli CSN1 Settembre 2005 56
Next 2 months : critical path22 Sept : BT jacks released
26 Oct : Calo barrel in
BT platforms removal
BMS Ce/C
HS arches Ce/C
Many activities running in parallel and superimposed
Critical delivery of material : rails, brackets, cable trays, gas manifolds, ..
Critical the readiness of the barrel calo : ID piping
BT current l. + cryoring (sec 5)
After calo barrel in (26 October to 22 Dec)
• Endcap C calorimeters assembly up to end Jan ‘06 on side C
• Connect BT services (vacuum, power, cryo, bus bars,…)
• Finish installation of mu-rails, mu-services, mu-installation tools
• Connect LAr/Solenoid Cryo services
• Install barrel muon chambers (6/day), from mid Nov on both sides
• Install calo services
• Install ID services (pipes and cables)
• Install cooling and gas racks + connections to in/out
• Commission detectors during installation (I.e. Calo in situ electronics,..)
• Maintain infrastructure operational
L.Mandelli CSN1 Settembre 2005 57
L.Mandelli CSN1 Settembre 2005 58
Schedule barrel• Driven by ID cabling dressing on calo flange (we assume
50cables/day)
• Hudge ID work with major unknowns (method, cables availability, sequence tuning,…)
• Plan to finish most chambers installation by Apr ‘06
• Plan to finish Calo C assembly by end Jan ‘06
• Calo C in by mid Feb ‘06
• Calo A start assembly Feb ‘06 to May ‘06
• Feb to Apr : magnets tests, solenoid field mapping
L.Mandelli CSN1 Settembre 2005 59
Forward region + ID• As soon as Calo C is in, install TAS shielding
• From end Feb ‘06 start Wheels C installation
• ECT C ready for installation from Sep ‘06
• As soon as Calo A is in, install TAS shielding
• ECT A ready for installation from mid Jun ‘06
• From Sep ‘06 we might start Wheels A installation
• Barrel ID installation end May ‘06 from side A
• ID A&C late summer ‘06
L.Mandelli CSN1 Settembre 2005 60
Forward region + ID• Interplay between ECTs and wheels to be optimised
• ECT C installation schedule & wheels A will strongly depend on experience on previous ECT A / Wheels C assembly
• We need to minimize LAr cold movements to avoid risks
• We need to minimize ECT risks, magnet test as soon as possible!
• We need to delay as much as possible the pixel installation (recent corrosion problems)
First discussions next week TMB/EB
Next 6 months planning to be fixed in Oct ATLAS week